Hi,

those tasks in project in which the users have submitted timesheet entries
and manager approved those entries .

if i want to delete those tasks from project through project professional
or change resources on those tasks in which resources have submitted time
sheets hours.
project professional are not changing resources on these tasks and not
deleting these tasks and displaying dialog boxe.

"Cannot delete or reassign tasks or assignments with protected actuals.
This task/assignment has protected actuals so it cannot be
deleted/reassigned."

how i can delete those tasks and change resources from them .
because manager dont need those tasks .

regards

basim alvi
 
T

texasroy

Basam:

Have the resources that have actuals submitted send a new timesheet for
those weeks whereby they "Delete" the hours for the tasks in question. If
you want to keep this effort, add a line in Op Support or some other project
to where they can transfer this effort. After they delete from their
timesheets and re-submit and you "Update" it, you can then delete the task.