About to Pause the Tasks

B

Basim

Hi ,

I want to pause some tasks which I want to do after some days and those
tasks must be disabled on the time sheet and on project professional and
project professional will not show me indicator that tasks are pass due date
..
and after some days I will enabled those tasks and user can enter the hours
and work on it.

Regards

Basim
 
R

RickD

Split the task and move the 2nd part out to where you think it will resume
and Publish New & Changed.
 