V
Vitek
Hallo All
How can I do following?
A resource got Task1 (50h). He wants to be able to insert subtasks,
BUT:
When he inserts Subtask1 with Work=5, he doesnt want to get a change
that Task1 has 55h now. He wants to get Task1=50h.
Commonly the inserting new tasks add hours. I want to insert new tasks
without affecting Work field, moving project(tasks) dates and so on.
Is it ever possible? And how about P03?
I have P2002+Server, hours/day tracking.
Thank you even for negative answers.
Vitek
(e-mail address removed)
How can I do following?
A resource got Task1 (50h). He wants to be able to insert subtasks,
BUT:
When he inserts Subtask1 with Work=5, he doesnt want to get a change
that Task1 has 55h now. He wants to get Task1=50h.
Commonly the inserting new tasks add hours. I want to insert new tasks
without affecting Work field, moving project(tasks) dates and so on.
Is it ever possible? And how about P03?
I have P2002+Server, hours/day tracking.
Thank you even for negative answers.
Vitek
(e-mail address removed)