hey,

is it possible to create an "abstract" timeline in Visio 07? I.e. it should
not be related to actual dates but only depend on duration of intervals for
example.
Most imporantly I want to display the duration in days, so that it does not
start counting again with a new month.
Example: Interval 1: 12 days - 2: 25 days - overall timeline: 37 days

I guess this question does also apply to MS Project then.

Thx,
Spoo
 
A

Al Edlund

The timeline add-in is specific to dates, so it might be more appropriate to
use MS project.