L
lude94
When updating actuals from timesheets (PWA) to the schedules, after selecting
Accept All then Update, the following error message appears:
"You need Microsoft Project Professional 2002 or Microsoft Project
Professional 2003 in order to perform this action.
If you are using either of these versions, verify that a correct account for
this Project Server as been set up and selected by pointing to Enterprise
Options (Tools menu) and then clicking Microsoft Office Project Server
Accounts. If you are unable to start Project with the correct account,
contct your server administrator to make sure that the enterprice features
have been enabled on the Project Server."
This appears regardless of whether MS Project is opened or not. User is
able to update the live schedules and take ownership or various schedules
without any problems.
Has anyone had any similar experience or know how to resolve this issue?
Accept All then Update, the following error message appears:
"You need Microsoft Project Professional 2002 or Microsoft Project
Professional 2003 in order to perform this action.
If you are using either of these versions, verify that a correct account for
this Project Server as been set up and selected by pointing to Enterprise
Options (Tools menu) and then clicking Microsoft Office Project Server
Accounts. If you are unable to start Project with the correct account,
contct your server administrator to make sure that the enterprice features
have been enabled on the Project Server."
This appears regardless of whether MS Project is opened or not. User is
able to update the live schedules and take ownership or various schedules
without any problems.
Has anyone had any similar experience or know how to resolve this issue?