S
susiew32
I have a small project with about 20 tasks and 5 resources, mostly for seeing
what Project can do for the project managers in our firm. I did levelling to
resolve conflicts ( which i put in on purpose to see what happens). It
worked nicely. Some of the suggestions I'd like to keep, some I don't. Is
there a way to accept a conflct resolution for one task and reject for
another task, then integrate the changes into my intial plan, without
maintaining levelling delay days?
Thanks in advance.
what Project can do for the project managers in our firm. I did levelling to
resolve conflicts ( which i put in on purpose to see what happens). It
worked nicely. Some of the suggestions I'd like to keep, some I don't. Is
there a way to accept a conflct resolution for one task and reject for
another task, then integrate the changes into my intial plan, without
maintaining levelling delay days?
Thanks in advance.