A
Angela
On Monday, I went into PWA and accepted several task updates from resources.
Seemed like everything was fine until I opened the project plan. None of the
task updates were applied to the project plans. I'm having this problem with
3 of my plans. This is what I have done so far to try and figure it out:
- Cleared local cache
- Went to "Applied Task Update Requests and Errors" page to see if there
were any errors. The tasks are highlighted in a reddish-pink color and in
the indicator column there is a red 'X' that says "The update was applied
successfully" when you hover over it. But they arent...
- I tried selecting the tasks that are highlighted and publishing.
- Had one of my resources submit his task updates from last week again.
I'm running out of ideas... your help is much appreciated!!!
Angela
Seemed like everything was fine until I opened the project plan. None of the
task updates were applied to the project plans. I'm having this problem with
3 of my plans. This is what I have done so far to try and figure it out:
- Cleared local cache
- Went to "Applied Task Update Requests and Errors" page to see if there
were any errors. The tasks are highlighted in a reddish-pink color and in
the indicator column there is a red 'X' that says "The update was applied
successfully" when you hover over it. But they arent...
- I tried selecting the tasks that are highlighted and publishing.
- Had one of my resources submit his task updates from last week again.
I'm running out of ideas... your help is much appreciated!!!
Angela