Accepting Tasks but unable to find out in plan time

M

MK

I have a user that believes that they have accepted task time time into the
plan but I have no idea what task it is going against since I don’t have the
same task in the project plan. How does this synch up?

Ideas on how to find out?
 
D

Dale Howard [MVP]

MK --

Are you the manager of the project or is the other person the manager?
Whoever is the manager should do the following:

1. Launch Project Professional 2007 and connect to Project Server.
2. Open the project in question.
3. If prompted to review pending task updates, click the No button.
4. Launch the Internet Explorer and navigate to the Task Updates page in
PWA.
5. On the Task Updates page, click the Go To pick list and choose the
Applied Requests and Errors item.

This page shows the cumulative history of all task updates that were either
accepted or rejected by the project manager. From here, he/she should be
able to figure what updates he/she approved by comparing them with the tasks
in the enterprise project currently open. Hope this helps.
 
D

DogLBer

Dale, again many thanks for answering a subject that has been bugging me but
not enough to raise the issue. I just put this answer to good use. I'm am
simply amazed at your grasp of this tool. Thanks!
 
D

Dale Howard [MVP]

DogLBer --

You are more than welcome for the help, my friend! And thanks for your kind
comment about my grasp of the tool. Believe me, my knowledge of the tool
has not come without much pain and suffering! :)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top