i use ms access2000 and i have all table of ms project for
ex MSP_RESOURCES and MSP_TASKS and MSP_ASSIGNMENTS and
MSP_PROJECTS and calendar and data_calendar and all table
i create Manual non working and working and create a
calendar and resources and task and Assignment
then export to ms project but the percent complet is not
correct for ex i write 80% in msp task table but after
export i see ex.66%
please help me until deliver my project
i use ms access2000 and i have all table of ms project for
ex MSP_RESOURCES and MSP_TASKS and MSP_ASSIGNMENTS and
MSP_PROJECTS and calendar and data_calendar and all table
i create Manual non working and working and create a
calendar and resources and task and Assignment
then export to ms project but the percent complet is not
correct for ex i write 80% in msp task table but after