G
Gilgamesh
Hello,
I have no problems accessing the baseline dates for any task or resource in
my schedules, my question is not about that.
When I save an updated baseline MSP shows me the date that the original
baseline was set.
It is possible in VBA to access (or even overwrite) this date without
affecting the other baseline values.
Thanks
I have no problems accessing the baseline dates for any task or resource in
my schedules, my question is not about that.
When I save an updated baseline MSP shows me the date that the original
baseline was set.
It is possible in VBA to access (or even overwrite) this date without
affecting the other baseline values.
Thanks