Accessing The Project Calendar information

S

SupaSonik

Im trying to read all the information inside the Project Calendars but
it seems as though that is impossible. I need to know when the working
time is of all the calendars because Ive written a Scheduler that uses
MS-Project and it is very time-consuming to use TimeScaleValues.

If anyone know of a way please let me know.

Thanks in Advance!
SupaSonik
 
R

Rod Gill

Hi,

You could read the contents of the .mpp file using oledb: see the file
PJOLEDB.HTM for details. There is a CalendarExceptions table. Note however
that in Project 2007 there will be no oledb capability unless files are
saved in 2003 format.
 