Hi All,
I have trouble with this so thought a simple scenario would help
understanding and may help others, too.
4 tasks
2 people resources
Sept 1st start
7-day work week
No dependencies except people time & D noted below
Tasks in days (elapsed time):
Michele - A-4 days & B-1 day
Lola - C-2 days & D-2 days where D has a Finish to Start dependency on
A
Michele should be done in 5 days (end of day on Sept 5th)
Lola should be done in 6 days with a 2-day buffer between C & D
What is the best/easiest way to schedule these 4 tasks? One should be
able to enter the 4 tasks with their people resources and the one
dependency, then Project should automatically figure out the rest,
i.e. Michele cannot do Task B until she is finished Task A, but Lola
can start Task C right away.
Very much appreciated,
Michele
I have trouble with this so thought a simple scenario would help
understanding and may help others, too.
4 tasks
2 people resources
Sept 1st start
7-day work week
No dependencies except people time & D noted below
Tasks in days (elapsed time):
Michele - A-4 days & B-1 day
Lola - C-2 days & D-2 days where D has a Finish to Start dependency on
A
Michele should be done in 5 days (end of day on Sept 5th)
Lola should be done in 6 days with a 2-day buffer between C & D
What is the best/easiest way to schedule these 4 tasks? One should be
able to enter the 4 tasks with their people resources and the one
dependency, then Project should automatically figure out the rest,
i.e. Michele cannot do Task B until she is finished Task A, but Lola
can start Task C right away.
Very much appreciated,
Michele