Accrue cost after lag

J

JudithJubilee

Hello there,

I have various tasks that I have added resources to with
their own Standard Rates. I understand how to accrue cost
Prorated, Start and End but I would like the cost to be
accrued after a time, eg. 21 days, has passed. Could
anyone advise me on the best way to go about this?

Thankyou in advance
Judith
 
M

Mike Glen

Hi Judith,

Welcome to this Microsoft Project newsgroup :)

This facilitity is not built in to Project, but with some vba it might be
possible. Try posting on the developer newsgroup. Please see FAQitem: 24.
project newsgroups. FAQs, companion products and other useful project
information can be seen at this web address: http://www.mvps.org/project/.

Hope this helps - please let us know how you get on :))

Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top