T
Thaddeus
Ok, This is what I do now:
On a sheet, I tally hours per day worked in individual
cells and total thos cells into C17 for the total hours
for the week. Following that I have the formulas for
taxes and O/T etc. to arrive at a net pay per employee.
What I would like to do:
create a "comp time" cell. My desire is this,
C17 is the total hours/week,
I want to make D17 the amount of hours the emp. would
like to go to comp time.
Then I want E17 to be the cumulateing total.
My theory--C17 has "60hrs", I enter "8" in D17 and hit
enter, "8" in D17 disappears and C17 now says "52hrs" and
E17 now says "8hrs". The following week has a total
of "58hrs" in C17 and the employee wants "5hrs" added to
comp time, an entry of "5hrs" is made in D17 and C17 now
says "53hrs" and E17 says "13hrs".
Can this be done?
Thanks, Thaddeus
On a sheet, I tally hours per day worked in individual
cells and total thos cells into C17 for the total hours
for the week. Following that I have the formulas for
taxes and O/T etc. to arrive at a net pay per employee.
What I would like to do:
create a "comp time" cell. My desire is this,
C17 is the total hours/week,
I want to make D17 the amount of hours the emp. would
like to go to comp time.
Then I want E17 to be the cumulateing total.
My theory--C17 has "60hrs", I enter "8" in D17 and hit
enter, "8" in D17 disappears and C17 now says "52hrs" and
E17 now says "8hrs". The following week has a total
of "58hrs" in C17 and the employee wants "5hrs" added to
comp time, an entry of "5hrs" is made in D17 and C17 now
says "53hrs" and E17 says "13hrs".
Can this be done?
Thanks, Thaddeus