Hi,
could anybody give me advise how I can enter actual information about task
which started e.g. on Monday, actually finished on Friday, but duration of
them is 4 hours? In base plan it planned as started on Monday and finished on
Monday. Developer start it as planned, do 50% and can't work for 4 days.
Duration at the and still 4 hours, but act. finished at Friday. When I
entered in tracking view actual start and finish MSP automatically define
duration as 40 hrs. How to fix it?
Alerxander Barvinsky
Director of Operations Department
could anybody give me advise how I can enter actual information about task
which started e.g. on Monday, actually finished on Friday, but duration of
them is 4 hours? In base plan it planned as started on Monday and finished on
Monday. Developer start it as planned, do 50% and can't work for 4 days.
Duration at the and still 4 hours, but act. finished at Friday. When I
entered in tracking view actual start and finish MSP automatically define
duration as 40 hrs. How to fix it?
Alerxander Barvinsky
Director of Operations Department