V
Verossa
Here is a simplification of my scenario
One tas
Duration: 3 months
Task Type: Fixed Work
Resource Assignment: 2 Units @ £500.00 / da
Contour: Fla
MS Project assigns the hours across the three months as follows
Apr - Work (176h
May - Work (168h
Jun - Work (136h
'Actual Work' is booked on a monthly basis (resources send a sheet - this is inputed into the act.work in MS Project). In April the work booked is 100h - a shortfall of 76h. The remaining 76h should be allocated to 'work' fields for May / Jun only. However, MS Project assigns 36h to Jul as follows
Apr - Work (100h), Act.Work (100
May - Work (168h
Jun - Work (176h
Jul - Work (36h
Why is this? There is enough resource (2 units) to complete the task within the duration (3 months). Or am I mistaken
Can anyone explain what is happening
TIA to all who respond
Vers
One tas
Duration: 3 months
Task Type: Fixed Work
Resource Assignment: 2 Units @ £500.00 / da
Contour: Fla
MS Project assigns the hours across the three months as follows
Apr - Work (176h
May - Work (168h
Jun - Work (136h
'Actual Work' is booked on a monthly basis (resources send a sheet - this is inputed into the act.work in MS Project). In April the work booked is 100h - a shortfall of 76h. The remaining 76h should be allocated to 'work' fields for May / Jun only. However, MS Project assigns 36h to Jul as follows
Apr - Work (100h), Act.Work (100
May - Work (168h
Jun - Work (176h
Jul - Work (36h
Why is this? There is enough resource (2 units) to complete the task within the duration (3 months). Or am I mistaken
Can anyone explain what is happening
TIA to all who respond
Vers