action log of the changes made in the plan

N

nirit

hi,
my boss for who worked with much older versions of Ms project claims that
there is a way to record notes chronologicaly but not as a note attached to a
task. meaning, if i allocated a resource for a different use than what was
plan, or we decided to stop one task (elimintae it altough it was suppose to
run till the end) because it was apparent that it is unseccessful and to
start new task in order to replace it.
is it possible? how is it done, and in what way do i print it out?
thanks,
Nirit.
 
R

Rob Schneider

As far as I know this is not currently possible, nor do I recall it in
previous versions.

Instead, keep a running log of changes in a document (paper or electronic).


--rms

www.rmschneider.com
 
N

nirit

that is what is think as well...
he probably thought i like geese.. (goose chase)
thanks anyway.
 