Hello Everyone,
Here are the 2 other problems that we are having over here at the office:
1. Our Active Directory synchs with our resource pool in Project Server but
only with a single node. The members of our team are asigned to multiple
directory nodes, so automated resource synchronization does not work. Is
there a workaround to this problem that exists?
2. Resource availability reports still include projects with past completion
dates. We tried to set projects to 100% complete and closed all tasks to
update, but we did not see any change. Will these projects stay permanently
on resource reports?
Thanks,
Matty
Here are the 2 other problems that we are having over here at the office:
1. Our Active Directory synchs with our resource pool in Project Server but
only with a single node. The members of our team are asigned to multiple
directory nodes, so automated resource synchronization does not work. Is
there a workaround to this problem that exists?
2. Resource availability reports still include projects with past completion
dates. We tried to set projects to 100% complete and closed all tasks to
update, but we did not see any change. Will these projects stay permanently
on resource reports?
Thanks,
Matty