Active Directory Problem / Past Project Problem

M

MPG_Interactive

Hello Everyone,

Here are the 2 other problems that we are having over here at the office:

1. Our Active Directory synchs with our resource pool in Project Server but
only with a single node. The members of our team are asigned to multiple
directory nodes, so automated resource synchronization does not work. Is
there a workaround to this problem that exists?

2. Resource availability reports still include projects with past completion
dates. We tried to set projects to 100% complete and closed all tasks to
update, but we did not see any change. Will these projects stay permanently
on resource reports?

Thanks,

Matty
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top