J
Janus Morthorst
When using: "Active Directory Resource Pool Synchronization" as a scheduled
task (every night even at different clocks I have tried) the job are not
processing i the Project Server Queue:
The belowed example are made a lunchtime 12:44 PM.
(http://localhost/pwa is changed from my customers real names)
http://localhost/pwa/_layouts/pwa/Admin/queue.aspx
Queue Type Start Date End Date Project Name Job Type Job State %
1 Timesheet 03-11-2009 12:44 N/A Active Directory Sync (Enterprise
Resource Pool) Processing 0%
When manully, the job are executed in the Project Server Queue in a second:
Timesheet 03-11-2009 13:29 03-11-2009 13:29 N/A Active Directory Sync
(Enterprise Resource Pool) Success 100%
I have in the ULS log (Central Administration > Operations > Diagnostic
Logging) set Error/verbose on "Project Server Active Directory
Synchronization" and are having the error below (http://localhost/pwa and
domain\serviceaccount are changed from my customers real names), those errors
are filling the ULS log up until I "Cancel" the Scheduled "Active Directory
Sync (Enterprise Resource Pool)"
11/03/2009 12:55:50.02 Microsoft.Office.Project.Server
(0x0FF8) 0x0F3C Project Server Project Server Active
Directory 8yjg Verbose PWA:http://localhost/PWA, SSP:SharedServices1,
User:domain\serviceaccount, PSI: Entering
HandleResourceUpdateErrors 11c18222-ef66-429e-ae3b-f1e9c7eafd27
11/03/2009 12:55:50.02 Microsoft.Office.Project.Server
(0x0FF8) 0x0F3C Project Server Project Server Active
Directory 8yjh Verbose PWA:http://localhost/PWA, SSP:SharedServices1,
User:domain\serviceaccount, PSI: Entering HandleResourceUpdateErrors, there
were errors 11c18222-ef66-429e-ae3b-f1e9c7eafd27
I have seen that others are having same problems, but I haven't found any
solutions
http://groups.google.co.il/group/mi....server/browse_thread/thread/e3cb09a3640aa224
I would appriciate anyone who could share or even explain the problem and
have to solve it?
Others customers facing same problem let me also here from you eventhough
you haven't found a solutions!
PS: The customer are running MOPS2007 SP2 no CU after SP2 (One APP, One WFE
and a Dedicated SQL as backend) on W2K3SP2 Server.
task (every night even at different clocks I have tried) the job are not
processing i the Project Server Queue:
The belowed example are made a lunchtime 12:44 PM.
(http://localhost/pwa is changed from my customers real names)
http://localhost/pwa/_layouts/pwa/Admin/queue.aspx
Queue Type Start Date End Date Project Name Job Type Job State %
1 Timesheet 03-11-2009 12:44 N/A Active Directory Sync (Enterprise
Resource Pool) Processing 0%
When manully, the job are executed in the Project Server Queue in a second:
Timesheet 03-11-2009 13:29 03-11-2009 13:29 N/A Active Directory Sync
(Enterprise Resource Pool) Success 100%
I have in the ULS log (Central Administration > Operations > Diagnostic
Logging) set Error/verbose on "Project Server Active Directory
Synchronization" and are having the error below (http://localhost/pwa and
domain\serviceaccount are changed from my customers real names), those errors
are filling the ULS log up until I "Cancel" the Scheduled "Active Directory
Sync (Enterprise Resource Pool)"
11/03/2009 12:55:50.02 Microsoft.Office.Project.Server
(0x0FF8) 0x0F3C Project Server Project Server Active
Directory 8yjg Verbose PWA:http://localhost/PWA, SSP:SharedServices1,
User:domain\serviceaccount, PSI: Entering
HandleResourceUpdateErrors 11c18222-ef66-429e-ae3b-f1e9c7eafd27
11/03/2009 12:55:50.02 Microsoft.Office.Project.Server
(0x0FF8) 0x0F3C Project Server Project Server Active
Directory 8yjh Verbose PWA:http://localhost/PWA, SSP:SharedServices1,
User:domain\serviceaccount, PSI: Entering HandleResourceUpdateErrors, there
were errors 11c18222-ef66-429e-ae3b-f1e9c7eafd27
I have seen that others are having same problems, but I haven't found any
solutions
http://groups.google.co.il/group/mi....server/browse_thread/thread/e3cb09a3640aa224
I would appriciate anyone who could share or even explain the problem and
have to solve it?
Others customers facing same problem let me also here from you eventhough
you haven't found a solutions!
PS: The customer are running MOPS2007 SP2 no CU after SP2 (One APP, One WFE
and a Dedicated SQL as backend) on W2K3SP2 Server.