B
BG_SAABer
Hi,
*The situation:* I have a MSProject 2003 where I have three tasks one
main task and two contained tasks. The main task has NO resources and NO
predecessors. The contained tasks have resources and chained
predecessors - second contained task begins after completion of the the
first contained task, while first contained task begins on fixed
calendar date. All tasks are marked as "FixedWork" in TaskType. The
"estimate" check-box is unchecked. No milestones, no explicit WBS codes,
no deadline, no constrains, and no calendar is configured. The "effort
driven" check-box is checked.
In the Gantt Chart I have a column called "Work" exposed.
*The problem:* When I change the value in input field "Duration"
(Advanced tab) the value in column Work for this particular task does
not get updated. Even worse. If I go to
Tools-->Tracking-->UpdateProject... , I get no update on the total sum
between the two contained task and their main task above. I can change
the value in the column Work, bit I can not make it to be linked to the
value in input field Duration. Also after running
Tools-->Tracking-->UpdateProject the value in input field Duration get
modified in some mysterious way.
*Question:* what is the proper way to link values in input field
Duration with rest of the project so that value in column Work properly
updates the amount of total time particular task requires to be
completed?
Thank you in advance.
*The situation:* I have a MSProject 2003 where I have three tasks one
main task and two contained tasks. The main task has NO resources and NO
predecessors. The contained tasks have resources and chained
predecessors - second contained task begins after completion of the the
first contained task, while first contained task begins on fixed
calendar date. All tasks are marked as "FixedWork" in TaskType. The
"estimate" check-box is unchecked. No milestones, no explicit WBS codes,
no deadline, no constrains, and no calendar is configured. The "effort
driven" check-box is checked.
In the Gantt Chart I have a column called "Work" exposed.
*The problem:* When I change the value in input field "Duration"
(Advanced tab) the value in column Work for this particular task does
not get updated. Even worse. If I go to
Tools-->Tracking-->UpdateProject... , I get no update on the total sum
between the two contained task and their main task above. I can change
the value in the column Work, bit I can not make it to be linked to the
value in input field Duration. Also after running
Tools-->Tracking-->UpdateProject the value in input field Duration get
modified in some mysterious way.
*Question:* what is the proper way to link values in input field
Duration with rest of the project so that value in column Work properly
updates the amount of total time particular task requires to be
completed?
Thank you in advance.