A
Adrian Wright
Hi all,
Our PS 2007 implementation is currently being used to simply(!) track time
and effort at a high level. We have many teams that have regular ongoing
activities to assign time to...such as IT support issues etc. Using Project
to set up project plans to capture this time against tasks does not seem to
fit as a best solution, as these tasks do not have end dates, and it is not
possible to accurately estimate work or resources required as much of the
work is reactive to unforeseen problems.
I have looked into Activity Plans as an alternative way of capturing this
time, but seem to only be able to assign one resource per task line, and am
also not sure if I can assign enterprise level fields, including custom
field, data to them.
Any advice greatly appreciated.
--
Adrian Wright
Project Administrator
MYOB
Victoria Australia
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...8ea12efad6&dg=microsoft.public.project.server
Our PS 2007 implementation is currently being used to simply(!) track time
and effort at a high level. We have many teams that have regular ongoing
activities to assign time to...such as IT support issues etc. Using Project
to set up project plans to capture this time against tasks does not seem to
fit as a best solution, as these tasks do not have end dates, and it is not
possible to accurately estimate work or resources required as much of the
work is reactive to unforeseen problems.
I have looked into Activity Plans as an alternative way of capturing this
time, but seem to only be able to assign one resource per task line, and am
also not sure if I can assign enterprise level fields, including custom
field, data to them.
Any advice greatly appreciated.
--
Adrian Wright
Project Administrator
MYOB
Victoria Australia
----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.
http://www.microsoft.com/office/com...8ea12efad6&dg=microsoft.public.project.server