Terri
Can anyone explain WHY Project moves the activity percent complete past the
status date?? My staus is Complete Through Friday 5:00PM, when I set the
status on an activity to Friday at 5:00PM, Project automatically moves the
percent complete through SUNDAY 5:00PM, or if Monday is a holiday, progress
move to Monday 5:00PM
Please don't tell me it is because Sat. & Sun. are not working days. Status
date is Friday, progress SHOULD NOT move past that set date.
The only time this works correctly in Project is on an activity with a 7 day
calendar.
I need a decent explanation for my PM (other than that's just what Project
does) why progress is showing through Sunday when the status date is Friday.
status date?? My staus is Complete Through Friday 5:00PM, when I set the
status on an activity to Friday at 5:00PM, Project automatically moves the
percent complete through SUNDAY 5:00PM, or if Monday is a holiday, progress
move to Monday 5:00PM
Please don't tell me it is because Sat. & Sun. are not working days. Status
date is Friday, progress SHOULD NOT move past that set date.
The only time this works correctly in Project is on an activity with a 7 day
calendar.
I need a decent explanation for my PM (other than that's just what Project
does) why progress is showing through Sunday when the status date is Friday.