S
Sophos
When a resource updates their task on PWA by 'Actual Work' and 'Remaining
Work', and the PM updates this on Project, something goes wrong:
If for example Task 1 was estimated to take 15h to do, but in fact the
resource took 7.5 hours to do and updated this on Actual Work as 7.5 and
Remaining Work as 0. When this is updated for the PM to update on Project
2003, Project does not schedule this so that it took 7.5h to do. Instead, it
updates it as 100% which is right but it is still scheduling this to have
taken 15h to do.
Is this something to do with the setting I have done? I have checked the
calenders and they are all right.
Work', and the PM updates this on Project, something goes wrong:
If for example Task 1 was estimated to take 15h to do, but in fact the
resource took 7.5 hours to do and updated this on Actual Work as 7.5 and
Remaining Work as 0. When this is updated for the PM to update on Project
2003, Project does not schedule this so that it took 7.5h to do. Instead, it
updates it as 100% which is right but it is still scheduling this to have
taken 15h to do.
Is this something to do with the setting I have done? I have checked the
calenders and they are all right.