M
Missy
My resources update me by "Hours of work done per day or per week: Resources
report the hours worked on each task during each time period". This is
reflected in MS Project when resources update me.
In the 'Work' view, the remaining and actual work is the same as what the
resources updated me which is what i want. However in the 'Entry' view its a
little bit different. Sometimes it works, sometimes it dont. For example, I
estimate the duration of Task A = 30h and the resource Actual work on it is
9h and remaining work 0. The duration decreases to 15h in Project.
I know that duration and Work mean 2 different things. What I dont
understand is why Project decreases this to 15h and not 9h. Yes all my task
types are 'Fixed Units'. Is project suppose to be doing this? If it is, then
i dont think this view is giving accurate info!
Hope someone out there knows what i am talking about!
report the hours worked on each task during each time period". This is
reflected in MS Project when resources update me.
In the 'Work' view, the remaining and actual work is the same as what the
resources updated me which is what i want. However in the 'Entry' view its a
little bit different. Sometimes it works, sometimes it dont. For example, I
estimate the duration of Task A = 30h and the resource Actual work on it is
9h and remaining work 0. The duration decreases to 15h in Project.
I know that duration and Work mean 2 different things. What I dont
understand is why Project decreases this to 15h and not 9h. Yes all my task
types are 'Fixed Units'. Is project suppose to be doing this? If it is, then
i dont think this view is giving accurate info!
Hope someone out there knows what i am talking about!