J
Jan Leeuwerink
Hi,
I am experiencing a odd problem. All tasks from different
subprojects are published to the project server. Now,
when some of the team members want to update their time
sheet, the actuals column on the right-hand side of the
sheet is blocked, it can't be updated, whereas other team
members can update that column. The users who can't
update the column can, however, update the "actual work"
and "remaining work" on the left-hand side of the
timesheet.
I would like to have all users updating the actuals on
the right-hand side of the timesheet.
The problem doesn't have to do anything with the "work
not scheduled for this period". I already checked that.
Thanks in advance.
Jan
I am experiencing a odd problem. All tasks from different
subprojects are published to the project server. Now,
when some of the team members want to update their time
sheet, the actuals column on the right-hand side of the
sheet is blocked, it can't be updated, whereas other team
members can update that column. The users who can't
update the column can, however, update the "actual work"
and "remaining work" on the left-hand side of the
timesheet.
I would like to have all users updating the actuals on
the right-hand side of the timesheet.
The problem doesn't have to do anything with the "work
not scheduled for this period". I already checked that.
Thanks in advance.
Jan