L
Lina
Example:
Project Date = January 1st
Task1 3 days/24 hours starting date of January 1st.
Task2 2 days/16 hours depending on completion of task 1.
1 hr/day resource assigned to task1 (completion will be in February)
How can I make task2 start at the actual completion date of task1 in
February, not on January 4th?
Thanks
Project Date = January 1st
Task1 3 days/24 hours starting date of January 1st.
Task2 2 days/16 hours depending on completion of task 1.
1 hr/day resource assigned to task1 (completion will be in February)
How can I make task2 start at the actual completion date of task1 in
February, not on January 4th?
Thanks