We have a number of projects in our Project Centre and currently use both
this view and the Portfolio Analyzer view. In both views we have 'actual
work' and 'actual cost' fields. For one of the projects the actual work is
the same (ie 112 hours) in both views but the actual cost is different. We
did change the rates in the global resource pool a couple of weeks ago but
none of the other projects appear to have this discrepancy. The figure in
the portfolio analyser is the correct figure.