Actual Cost not getting updated after the Resource Rate was changed.

R

rajanmisra

Hi all

We are working on Project Server 2003 , and follow the 'managed
time-period' method.

We had a resource working on a project for some time.

After that his rate got changed and at the same time he was added to a
second project , and he started reporting time on the second project.

The problem is that now in the 2nd project , he is having Actual Work
and Actual Work Protected values which are correct. But his Actual Cost
is showing 0. This is happening for the last two weeks.

The entire cycle of reporting time , approving time by managers has
been followed.
Does anyone have any idea about why this could be happening.

Thanks

Rajan
 