We are looking at implementing the use of rates in MSP Server 2003. Problem
is, that during my preliminary eval I noticed that if you manually enter
Actual Work on a task it appears to use the Actual Work value to perform the
Actual Cost calculation even though there is nothing in AWP.
Shouldn't the calculation be based ONLY on AWP?? Is there a way to lock it
down
is, that during my preliminary eval I noticed that if you manually enter
Actual Work on a task it appears to use the Actual Work value to perform the
Actual Cost calculation even though there is nothing in AWP.
Shouldn't the calculation be based ONLY on AWP?? Is there a way to lock it