I double-checked, and I do not have any material resources assigned.
However, I do have both fixed costs and resource driven costs (based on
resource assignments) to tasks. What I'm noticing is that the differences
between AC and ACWP are occuring on the tasks with resource assignments.
When I go to the Task Usage view and look at the resources assigned to the
task where there is a differece between the AC and ACWP, I find, for example,
that the Baseline and Actual Cost is $82.43 yet the ACWP is $164.85 for a
given resource. And sometimes the ACWP is less than the AC as well.
I'm just stumped as to why this is occuring- especially after a rebaseline.