G
Glenn
Hi all,
I have a task to build 5 miles of train track in 5 days, for $5000 at
$1000/day
I have a resource assigned at $125/hr or $1000/day. If after 1 day, I only
have 1/2 mile of track laid, then my earned value (BCWP) should be only $500
and my actual cost (ACWP) should be $1000. My resource is based on Fixed
Units, my Calculation is set to Automatic and my task is effort driven.
I enter the task info, save the baseline and BCWS, BCWP and ACWP are all
automatically calculated. For day one, each value is $1000. Great!
What I want is to have someone at the jobsite call me at the office and tell
me how much actually got done for the day as I already know I spent $1000 for
the day.
I have tried putting in fields such as Actual Work, % Work Complete, Actual
Cost, etc but it seems that % Work Complete and % Complete are the same thing
so I never see my BCWP change from $1000 down to $500.
How can I set things up or better yet where can I enter in the ACTUAL amount
that was done and compare that to what was ACTUALLY spent?
Glenn
I have a task to build 5 miles of train track in 5 days, for $5000 at
$1000/day
I have a resource assigned at $125/hr or $1000/day. If after 1 day, I only
have 1/2 mile of track laid, then my earned value (BCWP) should be only $500
and my actual cost (ACWP) should be $1000. My resource is based on Fixed
Units, my Calculation is set to Automatic and my task is effort driven.
I enter the task info, save the baseline and BCWS, BCWP and ACWP are all
automatically calculated. For day one, each value is $1000. Great!
What I want is to have someone at the jobsite call me at the office and tell
me how much actually got done for the day as I already know I spent $1000 for
the day.
I have tried putting in fields such as Actual Work, % Work Complete, Actual
Cost, etc but it seems that % Work Complete and % Complete are the same thing
so I never see my BCWP change from $1000 down to $500.
How can I set things up or better yet where can I enter in the ACTUAL amount
that was done and compare that to what was ACTUALLY spent?
Glenn