Hi good pple of the forum,
I am an Actual cost field in my schedule. Which automatically calculated
based on the standard rate of the resource multiplied by the number of hours
submitted by the resource when the assignment is updated. However, if a
resource updates his or her task, the actual cost field is automatically
updated in project office to reflect the actual cost put in.But this is not
the case in PWA, the actual cost field is not updated, i have to republish
the project schedule to get it updated in PWA.Please how do i get around this.
Thanks
I am an Actual cost field in my schedule. Which automatically calculated
based on the standard rate of the resource multiplied by the number of hours
submitted by the resource when the assignment is updated. However, if a
resource updates his or her task, the actual cost field is automatically
updated in project office to reflect the actual cost put in.But this is not
the case in PWA, the actual cost field is not updated, i have to republish
the project schedule to get it updated in PWA.Please how do i get around this.
Thanks