J
Jaya
Hi All...
Got some questions, if you could help will be truly appreciated:
1. Just wanted to confirm, when I start planning in Microsoft Project, I
estimate the Start/Finish Date through Start/Finish Field? Is that the way
it’s supposed to be done or should I estimate through the baseline
start/baseline finish field? the Actual Start Date/Actual Finish Date should
show up according the actual date started rite?
2.In Microsoft Project 2003, In the Tools Menu => Customize => Published
Fields, I have added new fields and it now appears in Web Access, but the
Actual Start and Actual Finish is 'NA', why is that? If I start the task
today, whether the estimate date is yesterday...the actual start date is
supposed to be today's date, isn't it?
Thanks all.. .
Got some questions, if you could help will be truly appreciated:
1. Just wanted to confirm, when I start planning in Microsoft Project, I
estimate the Start/Finish Date through Start/Finish Field? Is that the way
it’s supposed to be done or should I estimate through the baseline
start/baseline finish field? the Actual Start Date/Actual Finish Date should
show up according the actual date started rite?
2.In Microsoft Project 2003, In the Tools Menu => Customize => Published
Fields, I have added new fields and it now appears in Web Access, but the
Actual Start and Actual Finish is 'NA', why is that? If I start the task
today, whether the estimate date is yesterday...the actual start date is
supposed to be today's date, isn't it?
Thanks all.. .