K
Kenneth
I have a somewhat philosophical (or perhaps design related) question.
If I spent 3 days last week working on a task, I would expect to see 3 days
worth of ‘Actual Duration’ on the task, summary task as well as at the
project summary level (assuming no other work was done on the project).
However, it appears that ‘Actual Duration’ at Summary Tasks and Project
Summary Task is calculated based on the “% Complete†field. While that may
sound logical, it does create some odd results. For example, if I create a
project with 2 summary tasks each with 2 detailed tasks. Then, track 3 days
of actual duration against my first detailed task, my 3 days of actual
duration on the task translates into 1.67 days at the Summary Task and 1.77
days at the Project Summary Task. In other words, someone looking at the
project level would get the impression that less than 2 days of work was
completed, when that is in fact not the case.
To make matters worse, the numbers will change when I create dependencies on
the project. While I understand the mathematical formula of ‘Actual
Duration’ = ‘Duration’ * ‘% Complete’, I believe it’s a mistake to perform
this calculation on the Summary Tasks and the Project Summary Task,
especially so when I’ve entered ‘Actual Duration’ and not ‘% Complete’.
In my opinion, ‘Actual Duration’ on the Project Summary Task should roll up
similar to how the ‘Duration’ field does.
Any thoughts would be appreciated.
Regards,
Kenneth
PS: On past projects, I’ve always used ‘Fixed Work’, which is why I haven’t
come across this issue before.
If I spent 3 days last week working on a task, I would expect to see 3 days
worth of ‘Actual Duration’ on the task, summary task as well as at the
project summary level (assuming no other work was done on the project).
However, it appears that ‘Actual Duration’ at Summary Tasks and Project
Summary Task is calculated based on the “% Complete†field. While that may
sound logical, it does create some odd results. For example, if I create a
project with 2 summary tasks each with 2 detailed tasks. Then, track 3 days
of actual duration against my first detailed task, my 3 days of actual
duration on the task translates into 1.67 days at the Summary Task and 1.77
days at the Project Summary Task. In other words, someone looking at the
project level would get the impression that less than 2 days of work was
completed, when that is in fact not the case.
To make matters worse, the numbers will change when I create dependencies on
the project. While I understand the mathematical formula of ‘Actual
Duration’ = ‘Duration’ * ‘% Complete’, I believe it’s a mistake to perform
this calculation on the Summary Tasks and the Project Summary Task,
especially so when I’ve entered ‘Actual Duration’ and not ‘% Complete’.
In my opinion, ‘Actual Duration’ on the Project Summary Task should roll up
similar to how the ‘Duration’ field does.
Any thoughts would be appreciated.
Regards,
Kenneth
PS: On past projects, I’ve always used ‘Fixed Work’, which is why I haven’t
come across this issue before.