T
tshad
I want to be able to track the progress of my project by using the % Work
Complete instead of inputting actual hours in the Actual Duration column.
The problem is that I am not really looking at how many hours have been done
on a task but how much is complete. If I put hours in the Actual Duration
then I can see the progress on the timeline (black bar inside the blue one).
But the % Work Complete shows %0 until I acutally finish the task. The it
show 100%.
If I set the % Work Complete to 50% nothing happens on either the Work Done
or the Graph. Same if I put 100%?
How can I set it so I can use percentage complete - or can I?
Thanks,
Tom
Complete instead of inputting actual hours in the Actual Duration column.
The problem is that I am not really looking at how many hours have been done
on a task but how much is complete. If I put hours in the Actual Duration
then I can see the progress on the timeline (black bar inside the blue one).
But the % Work Complete shows %0 until I acutally finish the task. The it
show 100%.
If I set the % Work Complete to 50% nothing happens on either the Work Done
or the Graph. Same if I put 100%?
How can I set it so I can use percentage complete - or can I?
Thanks,
Tom