Actual durations

D

Dick

Hello. Is there a way to show durations in actual days
(or months) instead of just working days?
 
R

Rod Gill

Hi,

Durations are always shown in working days. However you can create a formula
(Project 2000+) that calculates the elapsed time between start and finish
dates and display that.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/