3
303588
I am a MS EPM server admin at a fortune 100 company. Running 2003.
Using % complete to update project tasks via PWA for users. When they
put a task to 100%, it records the baseline finish as the actual
finish, every time. I need it to record when the task was actually
put at 100%. Same with Actual start dates. Need the actual start
date to be the first time a task is accepted as > 0%. Any ideas?
Using % complete to update project tasks via PWA for users. When they
put a task to 100%, it records the baseline finish as the actual
finish, every time. I need it to record when the task was actually
put at 100%. Same with Actual start dates. Need the actual start
date to be the first time a task is accepted as > 0%. Any ideas?