D
Denise
We are currently using MS Project in a PWA Environment to track Actual Start
and Finish dates of a project. The projects are created from pre-defined
templates the calendar is set to use 9 hour work days 7am - 5pm. Each
project has many tasks assigned to different "Resource" personell which the
users view via PWA. The User can input the "Actual Start and Finish Dates"
but when the changes are published the "Actual Finish" date is not
(displayed) correctly in PWA. The date is correctly stored in the project
which is verified via Project Center. The transaction history for the Task
also shows the correct dates but shows a time of 8am not our calendars 7am.
The date is incorrect on the "My Task" page and in the "Task Properties"
input area. The duration is also incorrect and in partial days,ex 25.889d.
when it should be 30d.
I have documented the errors and can email them to anyone that has time to
look.
Thank you in advance for any help.
and Finish dates of a project. The projects are created from pre-defined
templates the calendar is set to use 9 hour work days 7am - 5pm. Each
project has many tasks assigned to different "Resource" personell which the
users view via PWA. The User can input the "Actual Start and Finish Dates"
but when the changes are published the "Actual Finish" date is not
(displayed) correctly in PWA. The date is correctly stored in the project
which is verified via Project Center. The transaction history for the Task
also shows the correct dates but shows a time of 8am not our calendars 7am.
The date is incorrect on the "My Task" page and in the "Task Properties"
input area. The duration is also incorrect and in partial days,ex 25.889d.
when it should be 30d.
I have documented the errors and can email them to anyone that has time to
look.
Thank you in advance for any help.