H
Hall
I have a 500-task plan covering 6 months. The fields Start and Duration
specify the schedule and all tasks have specified predecessors (finish to
start, start early as possible).
As time goes by, the gap between actual dates and planned dates, as often
happens in a project, grows. This makes the plan less useful unless I play
around with the planned fields.
How do I use this tool so that when I enter a date in the field Actual
Finish, all incomplete successor tasks have their Start date recalculated?
MS Project does work this way, right?
specify the schedule and all tasks have specified predecessors (finish to
start, start early as possible).
As time goes by, the gap between actual dates and planned dates, as often
happens in a project, grows. This makes the plan less useful unless I play
around with the planned fields.
How do I use this tool so that when I enter a date in the field Actual
Finish, all incomplete successor tasks have their Start date recalculated?
MS Project does work this way, right?