D
Daniel Zitter - Matan Consulting
I'm working on MSP 2003 with SP2a installed. I set a reporting method in PWA
where the resource reports Actual Start and Actual Finish on his assignments.
For some reason, when a resource updates the Actual Finish, and the project
owner approves the update, the MSP pro opens and tells me that changes have
been made, but in fact the update to the finish date disappears. The systems
works well for Actual Start updates. Any ideas? Could SP2a BE the reason?
Should I have checked the Task option rather than the Assignment option when
choosing to update the "Actual" Dates?
Thanks,
Daniel
where the resource reports Actual Start and Actual Finish on his assignments.
For some reason, when a resource updates the Actual Finish, and the project
owner approves the update, the MSP pro opens and tells me that changes have
been made, but in fact the update to the finish date disappears. The systems
works well for Actual Start updates. Any ideas? Could SP2a BE the reason?
Should I have checked the Task option rather than the Assignment option when
choosing to update the "Actual" Dates?
Thanks,
Daniel