Actual Hour in OLAP cube isn't populated correctly

E

evanc24

Hi,


We are running MSP 2003 Pro and Server and implemented OLAP recently.
However, after the OLAP cube is built, actual hour from Portfolio
Analyzer shows zero but resources timesheets show the correct hours.
The cube is built using the Earliest Project Start Date and the Latest
Project Finish Date. I queried the table, msp_cube_assn_fact, and the
assn_work field show either zero or very small number which can only be

seen in scientific format.


Any help be greatly appreciated.


Evan
 
V

Vadim Bogdanov

Evan,

actuals submitted by resources need to be accepted by PMs and updated
project plans have to be published on server.
After that actuals go to OLAP.

Actuals only in timesheets are not enough.
 