L
Lisa H
I am the project administrator and have a Project Manager who has several
tasks starting on non-working days. Looking at the tasks in question, I see
that a resource has entered hours on a non-working day and that that day is
the same as the Start date for that task. Do the actual hours override the
start date for a task? What is the explanation for finish dates also ending
up on non-working days?
tasks starting on non-working days. Looking at the tasks in question, I see
that a resource has entered hours on a non-working day and that that day is
the same as the Start date for that task. Do the actual hours override the
start date for a task? What is the explanation for finish dates also ending
up on non-working days?