T
thall999
Can I have two columns: one that shows actual hours to accomplish a task and
one that shows the duration for the number of days to actually get the task
done. For example, a 2 hour task, but a resource has 5 days to get it done
in. When I choose the duration field and the actual work field, it doesn't
allow them to be different units.
one that shows the duration for the number of days to actually get the task
done. For example, a 2 hour task, but a resource has 5 days to get it done
in. When I choose the duration field and the actual work field, it doesn't
allow them to be different units.