P
PM Training 12
With several projects (not all), when resources enter their actual hours in
PWA, and the PM accepts time, we see the following symptoms:
1. The WORK does not change to match the actual hours entered for that task
for that day.
2. The WORK to be done is not pushed ahead.
For example, if a task has 8 hours of work for Monday, and the Resource
enters 4 hours for Monday, after the time is accepted, the WORK stays at 8
hours, and the work to be done is not pushed ahead.
Yet, if the PM overtypes the actual work, MS Project will change the WORK
and move the work-to--done ahead (which we think is normal behavior) When
the actual work comes through PWA, MS Project does not seem to recalculuate.
We created several simple test projects, and the PWA path works fine for the
simple test projects.
We are running SP2a.
Does anyone have any ideas? Thanks.
PWA, and the PM accepts time, we see the following symptoms:
1. The WORK does not change to match the actual hours entered for that task
for that day.
2. The WORK to be done is not pushed ahead.
For example, if a task has 8 hours of work for Monday, and the Resource
enters 4 hours for Monday, after the time is accepted, the WORK stays at 8
hours, and the work to be done is not pushed ahead.
Yet, if the PM overtypes the actual work, MS Project will change the WORK
and move the work-to--done ahead (which we think is normal behavior) When
the actual work comes through PWA, MS Project does not seem to recalculuate.
We created several simple test projects, and the PWA path works fine for the
simple test projects.
We are running SP2a.
Does anyone have any ideas? Thanks.