We are upgrading from Project 2000/Project Central (long overdue!) to Project
2007/PS2007. I'm trying to get it set up so that when resources enter their
actual hours on their timesheet and submit, the hours automatically submit as
task updates. I don't want resources to have to go to My Tasks and import
timesheets and submit again. Is there a way to do that?
Thanks,
Michelle
2007/PS2007. I'm trying to get it set up so that when resources enter their
actual hours on their timesheet and submit, the hours automatically submit as
task updates. I don't want resources to have to go to My Tasks and import
timesheets and submit again. Is there a way to do that?