Actual Material Usage

A

agarwalp

Hi,

I have defined a task. I assign 2 Material resources viz. MatA (2ft) &
MatB(4ft). Now i have a problem. How do i track the actual usage. i.e
if suppose instead of 2Ft only 1Ft of MatA is used how do i track that.
I tried adding the Actual work column, but it does not allow me to add
anything. If i view the resource usage it shows Work, but Actual work
is not populated how do i do that.
I short i want to track the planned materials vs Actual Materials.
Thanks

Pradeep
 
G

Gerard Ducouret

Hello Pradeep,
Insert the Actual Work row in the Resource Usage view : Format / Details...

Hope this helps,

Gérard Ducouret
 
A

agarwalp

Thanks for reply,

That is done but how does it get populated. You know we enter the
%complete which is for work complete. but if i say the work is
completed 100% but instead of planned usage of 10 units of materials, i
have used only 6 units how do i track that. I just wanted to track my
planned materials vs actual material consumed. So as we have Planned
date and actual date, can we have Planned resources and Actual
resources.
 
G

Gerard Ducouret

Hello,
In the Actual Work yellow cells, in the Resource Usage view, enter ... the
Actual Work. That's all. Don't enter the %Complete ! (Project could not know
how to spread it)

Gérard Ducouret
 