M
Missy
Resources are updating me on PWA using Actual and Remaining Work. If for
example the PM estimated that a task takes 15h to do, but the resource
finishes this early by typing 7.5h (Actual Work) and 0h (Remaining Work) and
updates this into Project (by the PM), Project DOES NOT schedule this in so
that it took less time to complete that task. It makes it 100% complete
(which is correct) but doesn't decrease the duration. However if it was the
opposite way round i.e. the task takes longer to do and the resource enters
the hours of work in PWA, this reflects it in Project.
I have made all my tasks 'Fixed Units', by selecting all the tasks and going
into Task Information and changing the task type then publishing it.
There must be a bug somewhere? A setting on PWA or MS Pro?
Please HELP!
example the PM estimated that a task takes 15h to do, but the resource
finishes this early by typing 7.5h (Actual Work) and 0h (Remaining Work) and
updates this into Project (by the PM), Project DOES NOT schedule this in so
that it took less time to complete that task. It makes it 100% complete
(which is correct) but doesn't decrease the duration. However if it was the
opposite way round i.e. the task takes longer to do and the resource enters
the hours of work in PWA, this reflects it in Project.
I have made all my tasks 'Fixed Units', by selecting all the tasks and going
into Task Information and changing the task type then publishing it.
There must be a bug somewhere? A setting on PWA or MS Pro?
Please HELP!