S
Steph
I have set up an admin plan for holidays and absences. We record actuals by
timeperiod using Project Web Access (entering hours worked on a daily basis
for each week).
When I enter actuals for 'normal' projects the total Actual work / Remaining
work columns get updated, to reflect the hours keyed for each day, once they
have been accepted into the project plan by the project manager.
For adminstrative projects, however, this isn't happening. The Actual work /
Remaining work columns are only reflecting the updates when viewed in the
actual project plan itself but not when viewing tasks via the Web Access
view.
Is this the way administrative projects are supposed to work or am I doing
something wrong?
Thanks,
Steph
timeperiod using Project Web Access (entering hours worked on a daily basis
for each week).
When I enter actuals for 'normal' projects the total Actual work / Remaining
work columns get updated, to reflect the hours keyed for each day, once they
have been accepted into the project plan by the project manager.
For adminstrative projects, however, this isn't happening. The Actual work /
Remaining work columns are only reflecting the updates when viewed in the
actual project plan itself but not when viewing tasks via the Web Access
view.
Is this the way administrative projects are supposed to work or am I doing
something wrong?
Thanks,
Steph