I am a newbie. I have entered all the tasks and the corresponding
material resources required. I want to see both planned vs actual dates
since i am new to MS project i have two problems.
1. How do i see both plannd dates and actual dates? When i do
Tools->Tracking->Update Task i can enter the Actual dates, but it
changes the schedule dates. (i have baselined the schedule).
2. How do i reflect that in the Gantt chart?
Appreciate your help.
Thanks