G
Gary
I am a new user to MS Project and, of course, I'm having a few
difficulties getting Project to do what I want. Maybe I'm not
configuring it right, or maybe I'm not using it correctly. Either way
some advice would be very much appreciated.
Here's what I'm trying to do.
I'm trying to set up a task, with baselined start, finish, and work
values, such that I can enter the actual start, finish, and work
values, once known, and have them be what I want them.
For example, a task starts on Monday, finishes on Friday and takes 10
hours of work, even though the duration is 5 days.
I can set the initial values for this task okay, and I can also
capture the baseline for this task okay - I enter and display this
using the 'start', 'finish', 'work', 'baseline start', 'baseline
finish', and 'baseline work' columns.
My problem arises when I enter the actual values. I display the
actual fields using the 'actual start', 'actual finish', and 'actual
work' columns.
When I enter actual start, finish, and work values that are the same
as for the baseline everything is fine. However, for instance, if the
task in fact started on Tuesday, finished on Friday, and actually only
took 5 hours, I can't get all three values to match. I want to be
able to record that the task did actually start on Tuesday, finish on
Friday and take 5 hours, but when I enter Friday as an actual finish
date the actual work changes automatically to 8 hours, and when I set
the actual work to 5 hours, the actual finish date changes to NA.
I appreciate any help on how to set about doing this, in my mind, very
basic setup and recording.
Thanks,
Gary
difficulties getting Project to do what I want. Maybe I'm not
configuring it right, or maybe I'm not using it correctly. Either way
some advice would be very much appreciated.
Here's what I'm trying to do.
I'm trying to set up a task, with baselined start, finish, and work
values, such that I can enter the actual start, finish, and work
values, once known, and have them be what I want them.
For example, a task starts on Monday, finishes on Friday and takes 10
hours of work, even though the duration is 5 days.
I can set the initial values for this task okay, and I can also
capture the baseline for this task okay - I enter and display this
using the 'start', 'finish', 'work', 'baseline start', 'baseline
finish', and 'baseline work' columns.
My problem arises when I enter the actual values. I display the
actual fields using the 'actual start', 'actual finish', and 'actual
work' columns.
When I enter actual start, finish, and work values that are the same
as for the baseline everything is fine. However, for instance, if the
task in fact started on Tuesday, finished on Friday, and actually only
took 5 hours, I can't get all three values to match. I want to be
able to record that the task did actually start on Tuesday, finish on
Friday and take 5 hours, but when I enter Friday as an actual finish
date the actual work changes automatically to 8 hours, and when I set
the actual work to 5 hours, the actual finish date changes to NA.
I appreciate any help on how to set about doing this, in my mind, very
basic setup and recording.
Thanks,
Gary